How many days do you have to file a mechanics lien in Vermont?
A lien lasts no more than 180 days from the date payment became due for the last labor or materials unless a signed memorandum of the claim is filed with the town clerk of the town where the property is. Once filed, the lien relates back to the visible start of work or first delivery of materials.1 9 V.S.A. s. 1921(c) and s. 1923
Do you need a preliminary notice in Vermont?
A person who works under a contract with an agent, contractor or subcontractor of the owner must give the owner or the owner's agent written notice that they will claim a lien for labor or materials. The notice must include the date payment is due, if known. The lien reaches only the part of the contract price still unpaid when the owner receives the notice.1 9 V.S.A. s. 1921(b)
How long is a mechanics lien good for in Vermont?
Start a lawsuit and attach the property within 180 days after the memorandum was filed (or 180 days after payment becomes due, if it was not yet due at filing). After judgment, record a certified copy with the town clerk within five months to hold the property for the judgment.1 9 V.S.A. s. 1924 and s. 1925
Who can file a mechanics lien in Vermont?
A person who proceeds under a contract or agreement, written or oral, to erect, repair, move or alter improvements to real property, or to furnish labor or material for them, including through an agent, contractor or subcontractor of the owner.1 9 V.S.A. s. 1921(a), (b)
Does a Vermont lien claim have to be notarized?
The memorandum of the claim must be signed by the claimant; the statute does not require a notary acknowledgment.1 9 V.S.A. s. 1923
Public jobs: read the Vermont lien statute.
Sources
- 9 V.S.A. s. 1921(c) and s. 1923 (legislature.vermont.gov, 2026-10-27)