Texas mechanics lienNotice of claim and deadlines
The notice of claim is due the 15th day of the 3rd month after the month of work (2nd month on residential jobs)1. The lien deadline is the 15th day of the 4th month after the month you last furnished (3rd month on residential jobs)1; the deadline to sue is 1 year after the last day you could file the lien affidavit1.
Texas lien timeline
- First day of work
- 15th of month 3after first workNotice of claim (first month of work)1
- your workany lengthLast day of work
- 15th of month 4after last workFile the lien affidavit1
- 1 yearafter the filing deadlineSue to foreclose1
How many days do you have to file a mechanics lien in Texas?
Original contractor: affidavit with county clerk by 15th day of 4th month after month original work completed/terminated/abandoned (non-residential), 3rd month (residential). Other claimants: 15th day of 4th month after month last provided labor/materials (3rd month residential). Retainage claims: 15th day of 3rd month after original contract completed/terminated/abandoned.1 Prop. Code 53.052(a)-(d)
When is the Texas notice of claim due?
Derivative claimant sends notice of claim for unpaid labor/materials to owner and original contractor by the 15th day of the 3rd month after each month labor/materials provided (non-residential) or the 15th day of the 2nd month (residential). Statutory form required.1 Prop. Code 53.056(a-1)
How long is a mechanics lien good for in Texas?
Suit to foreclose no later than the first anniversary of the last day the claimant could file the lien affidavit; extendable to the second anniversary of affidavit filing by written agreement with owner before expiry.1 Prop. Code 53.158(a), (a-2)
Who can file a mechanics lien in Texas?
Person under contract with owner/agent/contractor/subcontractor who furnishes labor or materials, specially fabricates material, licensed architect/engineer/surveyor, landscaping, demolition.1 Prop. Code 53.021
Does a Texas lien claim have to be notarized?
Affidavit signed by claimant or another on claimant's behalf, containing a sworn statement of the amount of the claim.1 Prop. Code 53.054(a)(1)
What about public jobs in Texas?
Payment bond required for public work contracts over $25,000 ($50,000 for municipalities). Claimant mails notice to prime contractor and surety by the 15th day of the 3rd month after each month of work, with sworn statement of account; may sue if unpaid by the 61st day after mailing; suit barred after first anniversary of the date notice was mailed.2 Gov't Code 2253.021, 2253.041, 2253.073, 2253.078
Are there extra rules for homesteads in Texas?
Lien on homestead requires written contract executed before work begins, signed by both spouses if married.1 Prop. Code 53.254
How do you file a mechanics lien in Texas?
- Notice of claim (first month of work): due the 15th day of the 3rd month after the month of work (2nd month on residential jobs). Prop. Code 53.056(a-1) A derivative claimant sends a notice for each month with unpaid labor or materials; this date covers the first month.
- File the lien affidavit: due the 15th day of the 4th month after the month you last furnished (3rd month on residential jobs). Prop. Code 53.052(a)-(d)
- Sue to foreclose: due 1 year after the last day you could file the lien affidavit. Prop. Code 53.158(a), (a-2)
Each line restates the statute cited next to it. Check the statute text before you file.
Sources
- Prop. Code 53.056(a-1) (tcss.legis.texas.gov, 2026-10-27)
- Gov't Code 2253.021, 2253.041, 2253.073, 2253.078 (tcss.legis.texas.gov, 2026-10-27)